Marine Projects

As with our offshore projects and subsea projects - structures or components for the marine industry are also subjected to harsh conditions. Even though most of these structures or spools are not intended to be submerged in sea water - they still need a high level of corrosive resistance and durability. Structures of this nature is therefore often fabricated in adherence with NORSOK M-101, and either galvanized or surface treated with NORSOK M-501 System 7.

Guide Bumpers.png

01

Guide Bumpers

Rush fabrication for DeepOcean:

​

13 of 6'' S355J2 Guide Bumpers

NDT Cat. C: VT 100%, MT 20%

Surface Treatment: None

​

Fabricated in 16 days and in adherence to NORSOK M-101.

02

Anti-Biofuel Lens

Fabrication for Equinor Norne Ship:

​

1 of 24'' x 3'' x 2'', sch 20x40, 150# Carbon Blind Flange 

​

NDT 2: VT 100%, MT, RT 10%

Surface Treatment: System 1A, RAL WHITE 9002

​

Fabricated in adherence with NORSOK M-601.

IMG_5945_edited.jpg
Pipe Brackets.jpg

03

Pipe Brackets

Fabrication for DeepOcean:

​

29 of OD 152,4 Pipe Brackets

NDT Cat. C: VT 100%, MT 20%

Surface Treatment: Zinc Primed

​

Fabricated in adherence to NORSOK M-101.

04

Bumper Bars

Rush fabrication for DeepOcean:

​

4 of SHS 250 S355J2 Bumper Bars

NDT Cat. C: VT 100%, MT 20%

Surface Treatment: None

​

Fabricated in 12 days and in adherence to NORSOK M-101.